Open meeting of the Civil Procedure Rules Committee 2021 – Costs update

The CPRC annual open meeting took place today via Teams following last year’s successful online meeting. One of the benefits of the past year’s enforced remote working has been the ease of access to forums such as this. Hopefully as we come out of restrictions, we will be able to retain some of the positive changes alongside enjoying some face to face time.

The lessons of the past 14 months were covered by the Master of the Rolls, The Rt. Hon. Sir Geoffrey Vos, who discussed the need to be ambitious in delivering access to justice online and the real opportunities to improve. A lot has been learned in respect of video hearings and PDF bundles which has been great for the system. There will, of course, be instances where in person hearings are preferable but it is likely that shorter hearings will be able to continue to be dealt with remotely. The senior Judiciary will be taking the time to look at the matter carefully.

The following costs matters were discussed and the full minutes will likely be published in June:

Vulnerable parties – Last year changes were made to the overriding objective together with the introduction of PD1A in respect of vulnerable parties. Since then, as anticipated, the Domestic Abuse Act has received royal assent. Sections 64 and 66 require amendments to the CPR to make provision for special measures where a party is a victim or likely victim of domestic abuse. Sections 64 and 66 come into force in April 2022 and the committee has therefore embarked that work. The paper and drafts are due to come before the committee at July meeting.

Aldred -v- Cham [2019] EWCA Civ 1780  – The costs subcommittee has considered the issues rising from Aldred in respect of CPR 45.29I which covers recoverable disbursements in matters which no longer continue under the specified pre-action protocols. The rule includes a wrap up provision allowing for “any other disbursement reasonably incurred due to a particular feature of the dispute”. This provision was not wide enough according to the Court of Appeal and the Supreme Court panel said that the CPRC should consider the issue even though permission to appeal was refused. The key areas of concern were the fee for Counsel’s opinion where the Claimant is a minor (as required by CPR 21) and interpreter costs. In both cases the costs arose due to a characteristic of the Claimant rather than the dispute. The subcommittee’s proposed solution was to add those two specific instances to the list and to expand the wrap up provision to include any other disbursement which is required by the rules to be incurred. This was agreed and further discussion will take place off-line regarding other issues raised such as the costs of telephone conference fees.

Summary Assessment of Costs Pilot (PD51X) – The pilot was introduced in April 2019 to run to April 2021, however, following the pilot it was noted that uptake had been limited. It was therefore decided that the pilot would be extended for another year. It was generally agreed that whether parties are to file the old or new forms, they should be self calculating so that the judge can make changes. In respect of the N260A interim application pilot form, a concern is that a large amount of detail is required for simple hearings lasting maybe half an hour. In respect of the N260B for trial, it was noted that these may be fast track cases which are not budgeted and therefore practitioners are possibly not recording time in a compatible way. Possible fixed costs changes would also have an impact. There will be further informal consultation and a smart survey via the website is being considered to give feedback.

Costs consequences of late acceptance of Part 36 offers – The Lacuna committee has considered the issue arising from various recent cases including Pallett v MGN Ltd [2021] EWHC 76 (Ch) in respect of the tactical late acceptance of Part 36 offers by Defendants in order to avoid the automatic costs entitlement. The issue will be taken up by the costs subcommittee.

Form N170 & Costs – A question was raised regarding Form N170 (Listing questionnaire (Pre-trial checklist)) querying the requirement in section F that the parties must attach ‘an estimate of costs’  as this reference relates to the pre-April 2013 CPR costs regime and the old Practice Direction. The Forms subcommittee will look to amend this.  

You can find out more about our services here or you can contact the Costs and Litigation Funding team at CivilCosts@clarionsolicitors.com.

Part 36 – Important changes to Interest

From 1 April 2021 a key change to Part 36 means that additional interest will not be payable where the Part 36 offer is accepted after the relevant period unless specified within the offer.

In accordance with CPR 36.5(4) a Part 36 offer is treated as inclusive of any interest to the expiry of the relevant period. From 1 April 2021 a new rule 36.5(5) provides as follows:-

A Part 36 offer to accept a sum of money may make provision for accrual of interest on such sum after the date specified in paragraph (4). If such an offer does not make any such provision, it shall be treated as inclusive of all interest up to the date of acceptance if it is later accepted.

This rule change is likely to affect only claimants’ offers. However, defendants should be aware of the rule and check the terms of any offers received carefully.

At this stage the meaning of the rule is somewhat ambiguous. It is not clear whether it means that an offer may provide that if accepted after the expiry of the relevant period there will be a liability to pay further interest, or whether it simply means that the offer may exclude further interest from the terms of the Part 36 offer (i.e. the offer will become an offer for part of the proceedings after it has expired). These questions, and the effect of an offer which excludes interest, are only likely to be clarified when they have been put before the Courts. As the rule applies only to offers made on and after 1 April 2021, this is unlikely to be for some time.

You can find out more about our services here or you can contact the Costs and Litigation Funding team at CivilCosts@clarionsolicitors.com

Part 36 – is it unjust to award CPR 36 consequences when the defendant does not have the money to pay? (Rawbank -v- Travelex)

This article supplements and updates one titled Consequences of Beating a Part 36 Offer: Injustice published on 12 June 2019.

The case of Rawbank SA -v- Travelex Banknotes Limited [2020] EWHC 1619 (Ch) related to a contract that the Defendant would provide banknotes totalling in excess of $40 million to the Claimant. Due to the Coronavirus pandemic the Defendant was suffering from financial difficulties such that it could not fulfil its contract with the Claimant, and required restructuring. However, the Defendant had no defence to the claim, it was simply unable to fulfil its contractual obligations. Judgment was entered against the Defendant which was more advantageous to the Claimant than the terms of a Part 36 offer the Claimant had made.

Giving judgment in relation to the consequences of CPR 36, the Court allowed some of the consequences under CPR 36.17(4), but declined to allow an “additional amount” as provided for by CPR 36.17(4)(d). This decision reinforces a number of previous judgments in relation to the application of Part 36.17, specifically:-

  1. That the Court may adopt a cherry-picking approach and allow some of the consequences of CPR 36.17(4) but not others; and
  2. The court does not have discretion to award an “additional amount” at a rate other than 10% – it is all or nothing,

What is interesting about this case, however, is why the judge declined to make the award of the additional amount.

The Part 36 offer was made on terms that “the Defendant paid £48,290,000 within 14 days of accepting the offer…” At paragraphs 35 – 37 of the judgment, Zacaroli J held that “…acceptance of the Part 36 offer could only be made by actually paying the sum referred to in it…” and that because the Defendant was insolvent, “…it would be unjust to make at least some of the orders identified in Rule 36.17(4)”. The Court effectively found that because the Defendant did not have the money to pay the settlement sum, it could not have accepted the offer, and furthermore the fact of the Defendant’s impecuniosity meant that it would unjust to award the additional amount set out in CPR 36.17(4)(d).

In summary: a party’s financial position is a relevant consideration when considering the injustice test.

This decision appears to contradict, at least in part, the earlier authority of  Cashman -v- Mid Essex Hospital Services NHS Trust [2015] EWHC 1312 (QB), in which it was held that the court cannot take into account the amount of the additional amount when considering the test on injustice. It is a logical extension of that principle that the fact of a defendant’s ability or inability to pay is not a relevant consideration for the court to consider.

Furthermore, the judge appears to have erred in finding that the Part 36 offer ” could only be [accepted] by paying the sums referred to in it…” as CPR 36.14(7) provides that if the settlement sum “is not paid within 14 days of acceptance of the offer… the claimant may enter judgment for the unpaid sum”. It is plainly wrong to say that a party which accepts a Part 36 offer will then be bound to prioritise payment of the settlement sum above secured creditors (as was suggested at paragraph 35 of the judgment); the defendant will simply become liable to pay the amount of the settlement sum. If the defendant does not do so, then the claimant will be entitled to enter judgment. That judgment will be an unsecured debt and will be dealt with in an insolvency in accordance with the usual order of priority.

This decision appears to be a departure from previous authority and raises some significant uncertainty surrounding the meaning of “injustice” in the context of CPR 36.17, which many lawyers had hoped had been settled by a number of judgments in 2018 and 2019. It remains to be seen whether Rawbank will set a new standard by which the test of injustice is measured, or whether future courts will distinguish the case on the basis of its somewhat unique factual background. In either case, it can only be hoped that a case will find its way to a higher court to give some clarity on the question of what precisely “injustice” is.

Should you have any questions, you can contact the team at CivilCosts@clarionsolicitors.com

Part 36 – offer to pay by instalments

A party to proceedings (usually the defendant / paying party) may sometimes want to make an offer to pay the settlement sum by instalments. Whilst this is possible to do by Part 36, it does have an effect on the effect of the offer.

CPR 36.6(2) provides that a defendant’s Part 36 offer which offers to pay “all or part of the sum at a date later than 14 days following acceptance of the offer will not be treated as a Part 36 offer unless the offeree accepts”. The effect of this rule is that where a defendant makes an offer to pay by instalments:-

  1. If it is accepted then it will be treated in the usual way as a Part 36 offer. Therefore, Part 36.13 will apply (the defendant will pay the claimant’s costs up to acceptance, payment must be within 14 days etc);
  2. If it is not accepted and the defendant goes on to beat it, then CPR 36.17 will not apply.

It is important to note that this rule only applies to defendants’ part 36 offers – a claimant may make a Part 36 offer to accept payments by instalment and it will be treated as a Part 36 offer in the usual way.

The rules do appear to create a lacuna where a claimant makes a Part 36 offer including payments by instalments but where the offer includes a counterclaim or adverse claim. I am not aware of any existing authority on this point; it is likely that this is because this only affects a very small number of claims. In my view, it is likely that the court would construe such an offer as being a claimant’s offer for the purpose of CPR 36.6(2) unless it related solely to a counterclaim, in which case I think that it would be treated as being a defendant’s offer in accordance with CPR 20.2(2)(b).

Should you have any questions, you can contact the team at CivilCosts@clarionsolicitors.com

INTEREST IS NOT PAYABLE ON AN ADDITIONAL AMOUNT AWARDED UNDER CPR 36.17(4)(d)

Where the Court awards an “additional amount” under CPR 36.17(4)(d) as a claimant / receiving party beating its own Part 36 offer, the additional amount will not attract “enhanced” interest under CPR 36.17(4)(a).

In FZO -v- Adams & Anor [2019] EWHC 1286 (QB) the court allowed an additional amount under CPR 36.17(4)(d), but held that interest under CPR 36.17(4)(a) – enhanced interest at 10% above base rate – was not payable on that amount. Giving judgment, Mrs Justice Cutts found that the construction of CPR 36.17(4)(d) was that the “additional amount” was not a “sum awarded” and that the words “additional” and “amount” mean that the award is in addition to the enhanced interest at CPR 36.17(4)(a).

It should be noted that CPR 36.17(4) states that where the claimant has beaten their own offer the court “…must, unless it considers it unjust to do so, order that the claimant is entitled to…” and thereafter lists the consequences (enhanced interest, additional amount, etc). This does not appear to accord with the judge’s acceptance of the defendant’s submission that the additional amount is not a “sum awarded”. On the construction of CPR 36.17(4) it seems that those consequences are sums awarded by the court, albeit they are sums which the court is bound to award save where it considers it to be unjust.

Notwithstanding, the second strand of the judge’s reasoning appears wholly sound insofar as the “additional amount” is additional to the other consequences and therefore not itself subject to those consequences.

However, practitioners should be aware that this applies only to interest arising under CPR 36.17(4)(a). As the additional amount is a sum which a party is ordered to pay, and (as above) is a sum which the court orders that party to pay, it is a judgment debt and thus interest will, in the author’s opinion, arise under section 17 of the Judgments Act 1838 at the rate of 8% should payment not be made within the prescribed period (14 days pursuant to CPR 40.11 unless otherwise ordered)

Should you have any questions, you can contact the team at CivilCosts@clarionsolicitors.com

A PART 36 OFFER WHICH EXCLUDES INTEREST MAY BE VALID

A Part 36 offer in detailed assessment proceedings may be valid where it excludes interest under the Judgments Act 1838.

In Horne -v- Prescot (No.1) Ltd [2019] EWHC 1322 (QB) the Court held that a Part 36 offer on costs which excludes interest is a valid Part 36 offer, contrary to Ngassa -v- The Home Office [2018] EWHC B21.

CPR 36.5(4) states that a “part 36 offer… [for] a sum of money will be treated as inclusive of all interest…” In Ngassa it was held that therefore an offer which purported to exclude interest was not a valid Part 36 offer and therefore would not attract the consequences of Part 36.

However, in Horne the judge found that in detailed assessment proceedings, interest accruing under section 17 of the Judgments Act 1838 does not form part of the claim for costs, as it is a statutory entitlement in respect of which the Court is not required to make any finding. Therefore, unlike interest which may form a part of substantive proceedings (for example interest under the Late Payment of Commercial Debts (Interest) Act 1988) which forms part of the claim and must be Ordered by the Court, Judgments Act interest does not form a part of the “claim” for costs, and is not required to be ordered by the Court (though it may be disallowed).

Whilst the judgment in Horne is both legally sound and eminently sensible, as CPR 36 was not drafted with detailed assessment proceedings in mind (indeed until 2013 it was not possible to make a Part 36 offer in costs proceedings and is only now applicable due to a modification to Part 47 specifically applying Part 36 to detailed assessment) practitioners should bear in mind that Horne is a first instance decision and a different court on a different day may find differently. It may be prudent for practitioners to continue to include interest in Part 36 offers on costs until further authority clarifies the position. It is however a useful judgment to deploy where there is any dispute as to the validity of an offer.

Should you have any questions, you can contact the team at CivilCosts@clarionsolicitors.com

CONSEQUENCES OF BEATING A PART 36 OFFER: INJUSTICE

UPDATE [22/10/20] – the case of Rawbank -v- Travelex has introduced further matters for the court to take into account. Read more here:  Part 36: is it unjust to award CPR 36 consequences when the defendant does not have the money to pay 

There have been various cases recently on how the courts consider whether it would be “unjust” to apply the consequences of CPR 36.17. 

In White -v- Wincott Galliford Limited [2019] EWHC B6 (Costs) it was held that it would be unjust to allow an additional amount (CPR 47.17(4)(d)) for the whole of a claim where the offer had only related to some of the issues.

In Invista Textiles & Anor -v- Adriana Botes & Ors (costs judgment unreported) it was held that there is a high bar to demonstrate injustice. The ratio of the judgment suggests that the amount by which an offer has been beaten is at least not the only criterion which the Court should consider. Where a defendant / paying party seeks to argue that it would be unjust to allow some of all of the consequences of CPR 36.17 claimants / receiving parties would do well to refer to this authority as an example of the threshold for “injustice” which must be met.

It should also be noted that the court has previously held that the amount of the additional amount itself cannot be taken into account when considering whether it would be “just” to award the consequences of Part 36.17 per Cashman -v- Mid Essex Hospital Services NHS Trust [2015] EWHC 1312 (QB). In that case, the court on appeal held that the assessing officer had erred in refusing to award the additional amount “not because he considered the making of such an award unjust, but because he thought it unjust to make an award of the required amount”.

There is currently some inconsistency in the judicial approach to the application of the test of injustice. In the opinion of the author, the test is a high bar (supported by White and Invista) and the mere fact that the additional amount of 10% may appear high does not of itself render the consequence “unjust”. The consequences of CPR 36.17 are intended to be punitive and the purpose of the exception for “injustice” is not to allow judges to “soften the blow” to a litigant which has failed to accept a Part 36 offer, but to avoid genuine injustice where there are “exceptional” circumstances.

Should you have any questions, you can contact the team at CivilCosts@clarionsolicitors.com

Consequences of beating a Part 36 offer may be varied by the Court

***THIS JUDGMENT HAS NOW BEEN SUPERSEDED***

Senior Courts Costs Office extends the principle in JLE v Warrington & Hamilton Hospitals NHS Foundation Trust [2018] EWHC B18 (Costs).

In JLE  Master McCLoud held that where a Part 36 offer is beaten at a hearing, the Court has the power to consider the justness of each of the consequences of CPR 36.17 individually. In that case, the Court held that whilst it would not be unjust to allow costs on the indemnity basis or interest at the rate of 10% over base rate, it would be unjust to allow the uplift of 10% (often known as the “penalty payment”) given the amount by which the offer was beaten.

Following judgment in Andrews & Anor -v- Retro Computers & Anor [2019] EWHC B2 (Costs), there was a hearing to determine consequential orders on 5th March 2019.

Prior to the Oral Assessment of the Claimants’ costs, the Claimants had made Part 36 offers in the sum of £40,000. The bill of costs was ultimately assessed in the sum of a little more that £43,000 (inclusive of interest). Accordingly the Claimants submitted that they were entitled to the full range of orders under CPR 36.17. After finding that the Claimants should be entitled to additional interest and costs on the indemnity basis, Maser Friston considered whether or not to allow the “penalty payment” of 10% of the amount of the bill as assessed.

The Deputy Master pointed out that the Claimants had beaten the amount of the assessed bill by “only” 7.5%, and therefore considered that the uplift of 10% would be too high and therefore was minded to disallow the uplift under CPR 36.17(4)(d) on the basis that to do so would be unjust.

The Claimants submitted that pursuant to JLE the court had the power to “deconstruct” CPR 36.17 and to consider the unjustness or otherwise of each consequence individually, and that Master McCloud had held that the consequences of CPR 36.17 were not “all or nothing”. Therefore, they argued, that the Court had a general discretion not only to allow or disallow the penalty uplift, but where it considers that an uplift of 10% would be unjust, the Court may reduce the amount of the penalty uplift to a just level. The Court is therefore not constrained to disallow the penalty uplift in full if it considers that 10% is too high.

Following these submissions, Deputy Master Friston allowed an uplift of 7.5%, commensurate with the proportion by which the Claimants had beaten their offer.

Summary

The Court has the power to vary the percentage level of the uplift proscribed at CPR 36.17(4)(d). The proscribed rate is therefore a cap, not an entitlement, but if the Court finds that to allow the entirety of the 10% uplift would be unjust it is not bound to disallow the uplift entirely.

Every case will be decided on its own merits, but it seems reasonable that where a Claimant has beaten its own offer by less than 10%, the uplift should in principle be allowed in proportion to which the offer has been beaten.

The Claimants were represented by Richard Wilcock of Exchange Chambers, assisted by Matthew Rose of Clarion Solicitors.

The effect of Payments on Account on Part 36 and Judgment

The case of Gamal -v- Synergy Lifestyle [2018] EWCA Civ 210 has reinforced the position that a payment on account does not “increase” the value of a paying party’s Part 36 offer when considering whether the offer has been “beaten” for the purpose of CPR 36.17.

Case Summary

The original action between Synergy Lifestyle (the Claimant / Respondent), and Ms Nivin Gamal (the Defendant / Appellant) related to a claim for unpaid invoices. For ease of reading, the parties are referred to throughout as the Claimant and Defendant respectively. There were various issues relating to the fraudulent nature of the invoices, applicability of VAT, payment or a carpet in October 2013, and the level of costs payable as a result, however these have been omitted for the sake of simplicity and ease of reading.

29 October 2013 – Defendant paid the Respondent £6,600

October 2014 – Claim issued for £151,000

24 August 2015 – Defendant’s CPR 36 offer of £15,000

8 February 2016 – Defendant pays £10,000 to the Claimant

10 May 2016 – Judgment for the Claimant in the sum of £14,275.49 (assessed at £30,275.49 less £16,600 already paid by the Defendant in respect of that work) and the Defendant pay the Claimant’s costs.

The Defendant appealed on the basis that she had beaten the CPR 36 offer of £15,000 and that the judge had failed to properly apply CPR 36.17.

Judgment on Appeal

Giving Judgment, Flaux LJ placed great reliance upon the earlier authority of MacLeish -v- Littlestone [2016] EWCA Civ 127. In that case, Briggs LJ had held that a Part 36 offer was made to settle the entirety of the claim, and that admissions made by a defendant do not have the effect of modifying the Part 36 offer such that it applied only to those parts of the claim which remained in dispute (i.e. a Part 36 offer made in respect of the whole of the claim relates to the whole of the claim, whether or not part of that claim is subsequently admitted).

In Gamal, the court extended this principle to apply not only where a payment had been made following admissions but to any payment on account whether or not an admission had been made. The effect of the payment on account was to reduce the amount which the Defendant could ultimately be ordered to pay, and therefore to a corresponding reduction to the Part 36 offer. As such, the Court dismissed the appeal, held that the Part 36 offer had not been beaten, and upheld the award of costs.

Summary

In summary, the judgment reinforces what many would consider to be the “common sense” position. A payment on account is just that; a payment in anticipation of a future liability. It therefore does not have the effect of making a defendant’s offer more attractive or a claimant’s offer less attractive.

The discussion regarding a “reduction” to the Part 36 offer in the judgment may be somewhat confusing, however this is simply because there are two ways of looking at the issue:-

1. The court gave judgment for £23,675.49[1], distinct from the balance of £14,275.49 payable once credit was given for the payments applicable payments on account (i.e. those made after the date of the offer). Looked at in this way,  the Defendant had obviously not beaten her own offer.

2. The court gave judgment for £14,275.49 (as a result of the payments on account), however just as the payment on account reduced the judgment sum, it also reduced the level of the Defendant’s Part 36 offer (i.e. the offer of £15,000 became £5,000 once the payment on account was applied). This is the approach the court adopted.

Both of the approaches above arrive at the same conclusion though by different methods.

All practitioners should note that whether a payment is “on account” is open to judicial interpretation however the general presumption is that payments made during the currency of a claim are payments on account unless specifically stated otherwise.

Should you have any questions, you can contact the team at CivilCosts@clarionsolicitors.com

[1] In fact, the court assessed the value of the work at £30,275.49, which was necessary as the Claimant admitted that the invoices it had submitted were part of a fraud between it and the Defendant. However, the Claimant had already paid £6,600 towards this work in satisfaction of invoices prior to the commencement of proceedings. Therefore, the total value of the work done was found to be £30,275.49 but the total value of the claim against the Defendant was £23,675.49.